Show/Hide
  🚜 Notice: Temporary Relocation: The San Benito County Agricultural Commissioner’s Office has temporarily relocated.📍 New Location: 481 Fourth Street, 1st Floor, Hollister, CA 95023📞 Contact: 831-801-9225

🚜 Aviso: Reubicación Temporal: La Oficina del Comisionado de Agricultura del Condado de San Benito se ha reubicado temporalmente.📍 Nueva ubicación: 481 Fourth Street, 1er Piso, Hollister, CA 95023📞 Contacto: 831-801-9225

 Road Construction Map 




UNION ROAD REHABILITATION PROJECT UPDATE SATURDAY WORK APRIL 25, 2026

Post Date:04/24/2026 4:04 PM

PRESS RELEASE
FOR IMMEDIATE RELEASE

April 24, 2026    

UNION ROAD REHABILITATION PROJECT UPDATE
SATURDAY WORK APRIL 25, 2026    

SAN BENITO COUNTY, CA - The County of San Benito is providing an additional update on the ongoing Union Road Rehabilitation Project.

To support continued progress, construction activities are scheduled for Saturday, April 25, 2026, from 7:00 a.m. to 5:00 p.m. Work will include Full Depth Reclamation (FDR) microcracking operations as part of the roadway rehabilitation process.  

This activity will involve limited equipment, consisting of rollers/compactors and traffic control only. No heavy equipment or haul trucks will be in operation, and traffic impacts are expected to be minimal.  

Motorists should expect one-way traffic control with minor delays and are advised to use caution when traveling through the work zone, follow posted signage, and adhere to directions from construction personnel.  

The Union Road Rehabilitation Project, which began on March 23, 2026, remains on schedule and is anticipated to be completed by June 26, 2026, weather permitting.  

The County appreciates the public’s patience and cooperation as work continues to improve roadway conditions, safety, and long-term infrastructure reliability.  

###

Return to full list >>